Project Name: 1212 Infrastructure Upgrades
Address: 1212 Avenue of Americas
General Contractor; Pavarini McGovern
Client: Stawski Partners
Contract Amount: $5,500,000
Project Status: In Progress

Scope of Work

Cooling Tower Upgrade

  • Decommissioned and demolished in place two (2) existing cooling towers located on the 26th floor.
  • Rigged and installed three (2) new 1,000 GPM cooling towers on modified dunnage steel.
  • Installed new open loop condenser water pumps and associated controls.

Chiller Replacement

  • Demolished and removed of two (2) 330 ton steam absorption chillers.
  • Rigged and set four banks of water-cooled module chillers to the 25th floor MER from 6th Ave. A street shutdown and MTA permits were required.
  • Installed new chilled water pumps and associated controls.

Hot Water Boiler Plant

  • The building was converted from city steam to a new hot water boiler system.
  • Delivered and installed two 6,000 MBH BTU gas-fired hot water boilers.
  • Installed all new hot water piping and risers through the building.
  • Installed new hot water pumps and replacement the existing steam shell and tube heat exchangers with plate and frames to serve the secondary systems.
  • Demo of existing steam pre-heat coils with new hot water coils in the existing AHUS.

BMS Upgrade

  • Converted the existing base building pneumatic control system to all DDC controls. Installed new BMS
  • infrastructure and graphics for new and existing to remain equipment.